Assignment 7
Project to Arrange for Conference

Questions:
1. The table for this assignment provides best case, most typical case, and worse case estimates of task duration for each task. Using the PERT Beta distribution formulas, compute the expected time for achieving each task and its standard deviation.
2. How long will the project take to carry out?
3. What is the standard deviation of the critical path?
4. What is project duration when 1σ (standard deviation) is added? 2σ? (Note that when dealing with normal distributions, about 68% of observations lie within ±1 σ and about 95% of observations lie within ±2σ. We do not have a normal distribution in this case. We are working with a PERT Beta distribution that is not fully symmetric. Still, using an assumption of normality, we can get a very rough sense of the probability that a project will slip its schedule by 1σ or 2σ.)
5. Identify latest start, earliest start, and float times for each of the tasks in this project.

Expected duration Latest Start Earliest Start Float
ID speaker topics
Contact speakers
Select hotel
Arrange hotel accommodations
Arrange catering
Develop brochure
Print and mail brochure
Develop exhibit material
Develop workbook
Print and bind workbook
Final set-up for conference

6. An opportunity arises to have “Develop workbook” and “Print workbook” carried out earlier, in parallel to the other tasks. “Develop workbook” can begin as soon as “ID speaker topics” is complete. Reconfigure the PERT/CPM network to reflect this change in work. How much time has been saved on the project?


 

PLACE THIS ORDER OR A SIMILAR ORDER AND GET HELP

Click the button below to order this paper AND ENJOY OUR DISCOUNT.

The post The table for this assignment provides best case, most typical case, and worse case estimates of task duration for each task. Using the PERT Beta distribution formulas, compute the expected time for achieving each task and its standard deviation. appeared first on Deliver My Assignment.

I lOVE this Professional essay writing website. This is perhaps the fifth time I am placing an order with them, and they have not failed me not once! My previous essays and research papers were of excellent quality, as always. With this essay writing website, you can order essays, coursework, projects, discussion, article critique, case study, term papers, research papers, research proposal, capstone project, reaction paper, movie review, speech/presentation, book report/review, annotated bibliography, and more.

Post your homework questions and get original answers from qualified tutors!

PLACE YOUR ORDER

Share your love